Payment Records
Total Payment of 2,40,000 has been received
Due Amount
83,000 From the First Running Bill is Due.
Work Schedule
First Floor RCC
Completion Date: End of Falgun
Final RCC
Completion Date: End of Chaitra
All Brick Wall Complete
Completion Date: End of Baishakh
All Plaster Complete
Completion Date: End of Aashad
Payment Schedule
First Floor RCC
Completion Date: End of Falgun
Before RCC = 2,00,000 (Including Due Amount)
On the day of RCC= 2,06,000
Retention Amount II = 1,38,400
Final RCC
Completion Date: End of Chaitra
Before RCC = 0
On the day of RCC= 1,65,000
All Brick Wall Complete
Completion Date: End of Baishakh
After Completion=2,38,000
All Plaster Complete
Completion Date: End of Aashad
After Completion=2,40,900
Payment Breakdown
Ground Floor Work
2,00,000 (Including Wall Plaster and Boundary wall Work)
Frist Floor Work
1100 sqft @ 420 = 4,62,000
Second Floor Work
1100 sqft @ 420 = 4,62,000
Third Floor Work
395 sqft @ 420 = 1,65,900