Payment Records
No Payment has been received
Work Schedule
First Floor RCC
Completion Date: By First week of Jestha
Second RCC
Completion Date: First week of Aashad
Third RCC
Completion Date: First week of Shrawn
Top RCC
Completion Date: First week of Bhadra
All Brick Wall Complete
Completion Date: First week of Ashoj
Payment Schedule
After Foundation RCC (714*420 =299880)
On the day of RCC= 2,00,000
Retention Amount I = 99,880