Payment Records
2,00,000 HAS BEEN RECEIVED AFTER FOUNDATION WORK
Work Schedule
First Floor RCC
Completion Date: By First week of Jestha
Second RCC
Completion Date: First week of Aashad
Third RCC
Completion Date: First week of Shrawn
Top RCC
Completion Date: First week of Bhadra
All Brick Wall Complete
Completion Date: First week of Ashoj
Payment Schedule
After Foundation RCC (714*420 =299880)
On the day of RCC= 2,00,000
Retention Amount = 99,880
After First RCC Work (826* 420 =3,46,920)
Previous Retention Amount =99,880
Total Amount: 4,46,800
Retention Amount:1,34,040
Due Payment
3,12,760