Payment Records

  • 2,00,000 HAS BEEN RECEIVED AFTER FOUNDATION WORK

Work Schedule

  • First Floor RCC

    Completion Date: By First week of Jestha

  • Second RCC

    Completion Date: First week of Aashad

  • Third RCC

    Completion Date: First week of Shrawn

  • Top RCC

    Completion Date: First week of Bhadra

  • All Brick Wall Complete

    Completion Date: First week of Ashoj

Payment Schedule

  • After Foundation RCC (714*420 =299880)

    On the day of RCC= 2,00,000

    Retention Amount = 99,880

  • After First RCC Work (826* 420 =3,46,920)

    Previous Retention Amount =99,880

    Total Amount: 4,46,800

    Retention Amount:1,34,040

Due Payment

  • 3,12,760